ADOT's $62M SR 260 Project Heads Into Winter Hiatus

December 4, 2018 - West Edition #25
Arizona Department of Transportation

(ADOT photo)
(ADOT photo)

Due to a colder, wetter October than anticipated, final work on the State Route 260 widening project between Camp Verde and Cottonwood will take place next spring, including putting down the final pavement layer known as a friction course.

However, the Arizona Department of Transportation was able to complete all major work on the $62 million project this year. In the 9-mi. stretch, crews constructed two lanes in each direction separated by a median, opened seven roundabouts at major intersections and completed a new bridge over Cherry Creek near Cherry Creek Road.

All lanes and roundabouts between Interstate 17 and Thousand Trails Road will be open to traffic before the project shuts down for the winter. There will be no construction-related restrictions in place.

Original plans called for the final layer of pavement to go in before winter hiatus, followed by permanent lane striping in the spring. After unusually wet weather from remnants of Hurricane Rosa combined with a drop in temperatures, both of these final steps will be completed in the spring.

The road surface needs to be around 85 degrees in order for new pavement to cure properly.

ADOT's contractor had begun preparing the roadway for the final pavement layer when weather conditions forced the decision to finish next year. As a result, the road surface, while smooth and safe to drive on, will be a bit noisier than it otherwise would with the final pavement layer.

For more information, visit azdot.gov/SR260widening.


Today's top stories

New SR 141 Alignment Promises Smoother Travel Through Middle Tennessee

Webber–United JV Advances $620M I-16/I-75 Interchange

Thompson Tractor Hosts Companywide Used Equipment Sale

Georgia Power Begins Construction of Battery Storage System

Werk-Brau Names Gold Coast JCB as South Florida Dealer

BOMAG Names Mid South Machinery Full Line Dealer for State of Mississippi

Louisiana Breaks Ground On $2.3B I-10 Calcasieu River Bridge

James River Equipment Named Newest Trimble Technology Outlet, Serving Customers in Mid-Atlantic


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019