Create a CEG Account  /  CEG Login



CDOT's I-70 Resurfacing Project Nears Completion

CDOT's $34.7 million I-70 resurfacing project from Chief Hosa to Colfax nears completion, improving safety and travel time reliability. Financed by state and federal funds, the project includes bridge deck repairs, variable speed limits, and new storm drainage improvements.

April 15, 2026 - West Edition #8
Irwin Rapoport – CEG Correspondent

The Colorado Department of Transportation (CDOT) and its contractor, Martin Marietta, achieved substantial completion of the $34.7 million Interstate 70 resurfacing project from Chief Hosa to Colfax in December 2025.
Colorado Department of Transportation photo
The Colorado Department of Transportation (CDOT) and its contractor, Martin Marietta, achieved substantial completion of the $34.7 million Interstate 70 resurfacing project from Chief Hosa to Colfax in December 2025.
The Colorado Department of Transportation (CDOT) and its contractor, Martin Marietta, achieved substantial completion of the $34.7 million Interstate 70 resurfacing project from Chief Hosa to Colfax in December 2025.   (Colorado Department of Transportation photo) The initiative to improve safety, mobility and travel time reliability along a 10-mi. stretch of the mountain corridor is expected to conclude in 2026.   (Colorado Department of Transportation photo) Approximately 6,000 linear ft. of traffic lanes (2.27 lane mi.) was resurfaced on a typical shift.    (Colorado Department of Transportation photo) An overhead view of Interstate 70   (Estate Media photo) Paving often occurred during the overnight hours.   (Estate Media photo) The Genessee Bridge overlook   (Martin Marietta photo) The section of Interstate 70 recently revamped, winds through mountainous terrain.   (Martin Marietta photo) An average of 121,000 vehicles travel this stretch of I-70 each day.   (Martin Marietta photo)

The Colorado Department of Transportation (CDOT) and its contractor, Martin Marietta, achieved substantial completion of the $34.7 million Interstate 70 resurfacing project from Chief Hosa to Colfax in December 2025.

Colorado Department of Transportation photo

The initiative to improve safety, mobility and travel time reliability along a 10-mi. stretch of the mountain corridor is expected to conclude in 2026 when Lighthouse Transportation Group and Xcel Energy install an intelligent transportation system (ITS) that establishes variable speed limits.

Financed by state and federal funds, work began in August 2024.

‘‘We have improved safety by replacing deteriorating pavement for a smoother driving experience and installed new safety guardrail," Cody Daigneault, resident engineer with CDOT's Region 1 West Program, told Construction Equipment Guide. ‘‘The project repaired both bridge decks at the Morrison exit, increasing the structures' lifespan. We will also improve travel time reliability and mobility by installing dynamic speed limit signs and message boards on eastbound I-70 from Genesee Park to Colfax."

‘‘This stretch of I-70 is heavily traveled, serving as the gateway to the Rocky Mountains for tourists and is a critical link for freight trucks and local and regional traffic as well," he added. ‘‘Due to heavy wear and tear from freight and vehicle traffic, in combination with harsh winters, the pavement, bridges and other roadway assets were in need of repair to prevent potholes and other pavement damage."

The initiative milled and paved the existing lanes, repaired two bridge decks at the Morrison/Colorado 93 exit, installed storm drainage improvements, replaced guardrails and added variable speed limit signs and message boards on eastbound I-70 from Genesee Park (Exit 254) to Colfax (Exit 262/U.S. 6).

I-70 was built along with much of the mountain corridor in the 1960s through the 1970s. An average of 121,000 vehicles travel this stretch of I-70 each day.

Martin Marietta photo

The construction zone falls within the jurisdiction of the municipalities of Genesee and Golden in Jefferson County. This section of I-70 has three lanes in each direction.

Bill Oetken, Martin Marietta's West Division construction manager, praised Lead Project Manager Zach Schmidt and Project Managers Ryan Peters and Logan Baker for their effort and dedication.

‘‘My project team gave it their all to make this project a success and a final product that the traveling public could enjoy driving for trips across the country and to the mountains," Oetken told Construction Equipment Guide.

Four Projects in One

The project faced its share of challenges.

‘‘Construction challenges included the fact that this project consisted of four smaller projects wrapped into a single project," Schmidt told Construction Equipment Guide. ‘‘We had an ITS project, a drainage project, a structures project and an overlay project all tied into one large project, all of which required quick troubleshooting and critical thinking throughout the two-year-long project. The work progressed in a slower manner, as it was just starting up during the fall/winter months of 2024-2025.

"Once the weather cleared last spring, work was accelerated, and there were up to eight to 10 trades working at any given time. Multiple milling/paving crews were utilized to complete the paving in our short paving window due to the SMA [stone mastic asphalt] being an extremely volatile product that is weather dependent, and the nature of the paving taking place in the mountains, where our paving window was shrunk down to three to four months."

The only utility issue that crews encountered was the installation of new power lines from a third-party utility that were needed for activating the ITS system.

Colorado Department of Transportation photo

The work site was confined to the shoulders of the current interstate, with most of the work taking place overnight with single and double lane closures needed to perform work.

‘‘All day work was performed behind a shoulder closure, as the roadway was wide enough" Peters said. ‘‘Working with CDOT proved to be a challenge due to the work schedule of all parties involved with day and night work progressing and trying to line up everyone's schedules to get the proper answers and challenges resolved in a timely manner."

The resurfacing began on the eastbound (downhill) side, starting at the Chief Hosa exit. Once it reached Morrison, crews switched to the westbound (uphill) side.

‘‘Work was planned to install the new barrier/drainage runs in three phases along the westbound lanes," Baker said. ‘‘This work was anticipated to take approximately 10 months to complete. Once completed, milling and resurfacing were to begin after the Fourth of July holiday and take approximately 3-4 months to complete. All the while this work was ongoing, ITS work was taking place during the daytime hours and was anticipated to take the entire 320 working days to complete.

"Bridge deck rehab took place with the westbound bridge deck being completed in the fall of 2024, but the eastbound bridge deck would have to wait until the 2025 construction season due to the extensive amount of work that was required on the westbound deck."

Two at a Time

Baker said multiple lanes were milled/paved at once, which required two milling crews and two paving crews due to the short paving window in the mountains.

No repairs were made to the road's subbase or base. The new SMA lift thickness was 2.5 in.

Approximately 6,000 linear ft. of traffic lanes (2.27 lane mi.) was resurfaced on a typical shift.

Colorado Department of Transportation photo

Operators used Wirtgen milling machines — a W 250 XF and three W 220 Fis — two Weiler E1650 asphalt shuttle buggies, two Cat 1055F pavers and Cat asphalt rollers — two CB13s, two CB64s and two CB 16s — to repair the two bridge decks at the Morrison/CO 93 exit

Both bridge decks at the Morrison/Colorado 93 exit were scheduled for Oct. 31, 2024, completion, but that was pushed back until Memorial Day 2025.

‘‘The intent was to have both bridge decks being rehabilitated at the same time, but due to resources and logistical reasons, it was agreed upon by both parties that repairing the WB deck first, due to it being in the worst shape, was the best course of action and that the EB deck could wait until the following construction season," Schmidt said.

Each deck was approximately 200 linear ft. long and 50 linear ft. wide, with an additional 72 linear ft. of abutment.

‘‘The deck was to remain intact, and we fixed the potholed concrete through a process called sounding the deck," Schmidt said. ‘‘This process identifies degraded concrete by creating a hollow sound. Once an area for rehab was identified, it was jackhammered out, new rebar was installed and new Class DR concrete, batched on site, was poured into the void."

The bridge decks were constructed as a steel girder-concrete slab, allowing for containment within the girders so debris wouldn't fall to the roadway below.

Concrete Plans

Class DR concrete was used for the pour back of the deck rehab, and basic No. 4 black rebar was used.

Martin Marietta photo

‘‘On average, each deck required 17 pours to complete," Schmidt said. "Being that the Class DR concrete is a rapid-set concrete, the concrete was usually cured out and able to have traffic on it within 90 minutes of it being poured. Usually, in those 90 minutes, the concrete was achieving a strength of 2,500 psi."

Crews used jackhammers and an onsite portable concrete mixer for the process.

The installation of the storm drainage improvements was completed in three phases and concurrently with the barrier work.

‘‘The area for the new drainage was cut to grade, new inlets were installed and the new barrier was then poured in two sections — bottom half, and then top half)," Baker said. ‘‘Once the barrier was poured, new drainage line was placed. While the barrier was being poured in the previous phase, crews would move up to the next phase and begin digging out for the new barrier/drainage line in Phase II. Crews would then alternate between phases to make sure there were no breaks in either trade until the work was completed in all three phases."

An additional 41 inlets were installed along the three phases of the new drainage. The only prefabricated elements were the 18-in.' RCP that was installed. All inlets were cast-in-place throughout the corridor.

The existing guardrail was replaced with a 31-in. Midwest Guardrail system by Cruz Construction between March and August 2025.

‘‘Crews were to begin installing new guardrail prior to new pavement being put down due to the short paving window that we would have and the longer duration to install the guardrail prior to achieving substantial completion," Baker said.

Subcontractors included ABCO Contracting Inc., A-Core Concrete Specialists, Alpha Milling, American West Construction, B Jackson Construction and Engineering LLC, Colorado Barricade, Cruz Construction, Ellisco Profiling, Estate Media, H2 Enterprises, Lighthouse Transportation Group, Lobato Construction, Nelson Industrial Services Inc., Powell Restoration Inc., Prep-Rite Coatings and Contracting, PWSI Land Surveyors, Roadsafe Traffic Systems, Sam Rhoades Inc. and Workzone Traffic Control. CEG



Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.



Today's top stories

IDOT Transforms I-57 With $325M Expansion

USACE Handles Hangar Construction at Fort Riley, Kan.

Making Work Zones Safer

Hayden-Murphy Welcomes Guests to Elk River Open House

APWA Snow Conference Brings Industry Together in Cleveland

Royals, Hallmark Plan $3B Crown Center Stadium Project

New SR 141 Alignment Promises Smoother Travel Through Middle Tennessee

Webber–United JV Advances $620M I-16/I-75 Interchange


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019