Coast Guard Awards $200M Contract to Rebuild Station

The U.S. Coast Guard awarded The Haskell Co. a $200M contract to rebuild Coast Guard Station South Padre Island, enhancing border security and supporting military operations in Texas. Scheduled for completion in summer 2028, it marks a milestone in Coast Guard construction history.

March 2, 2026 - West Edition #5
U.S. Coast Guard

A rendering of the future U.S. Coast Guard Station South Padre Island, Texas
U.S. Coast Guard image
A rendering of the future U.S. Coast Guard Station South Padre Island, Texas

The U.S. Coast Guard announced on Jan. 14, 2026, that it awarded a $200 million design-build contract to The Haskell Co. for the comprehensive recapitalization and expansion of Coast Guard Station South Padre Island in South Padre Island, Texas.

The award marks the largest single task order in the history of the Coast Guard's military construction program.

The contract, funded through the One Big Beautiful Bill Act, will deliver the design and construction of more than 120,000 sq. ft. of essential facilities and supporting infrastructure, directly enhancing mission readiness and execution for Coast Guard and Customs and Border Protection personnel on the southwest U.S. border in Texas. Preliminary design and environmental work will begin immediately, with project completion anticipated in summer 2028.

Located 6 mi. north of the United States-Mexico border, Station South Padre Island is at the forefront of securing the U.S. southern border. The recapitalization project will support the Coast Guard's operations to secure the U.S. border and maritime approaches, facilitate commerce vital to economic prosperity and strategic mobility and respond to contingencies along the Gulf Coast and surrounding waterways.

The scope of work includes:

• environmental assessment, site survey investigations and design services for various facilities;

• construction of new station facilities;

• construction of unaccompanied personnel housing (UPH), additional berthing and mission support facilities;

• rebuilding of waterfront infrastructure;

• construction of a joint operations center and Customs and border protection support space;

• forward operations space for deployable specialized forces;

• delivery of a new harbor operations center and other mission support facilities; and

• comprehensive site development, utilities and outfitting.

The project represents the largest award value for a shore infrastructure construction project in Coast Guard history and will be delivered on the shortest timeline to date. The planning phase was compressed from the standard 18 months to 45 days, while the contracting process was reduced from 15 months to four months.

On April 20, 2025, a fire severely damaged the boat house at Station South Padre Island, forcing crews to relocate operations. The next day, station personnel responded to reports of illegal fishing and interdicted a vessel in the U.S. Exclusive Economic Zone, where they discovered 130 lbs. of red snapper and 75 lbs. of shark on board.

"The courageous team of Station South Padre Island showed resilience and determination," said Admiral Kevin Lunday, acting commandant of the Coast Guard. "The day after fire severely damaged facilities at Station South Padre Island, this crew was back on patrol, successfully interdicting illicit activity in one of our most complex operating environments. This project will provide Station South Padre Island with modern facilities and empower them to continue operations to control, secure and defend our southern border."


Today's top stories

IDOT Transforms I-57 With $325M Expansion

USACE Handles Hangar Construction at Fort Riley, Kan.

Making Work Zones Safer

Hayden-Murphy Welcomes Guests to Elk River Open House

APWA Snow Conference Brings Industry Together in Cleveland

Royals, Hallmark Plan $3B Crown Center Stadium Project

New SR 141 Alignment Promises Smoother Travel Through Middle Tennessee

Webber–United JV Advances $620M I-16/I-75 Interchange


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019