Crews Find Way to Speed Up Construction On I-5 Project

May 4, 2021 - West Edition #10
WSDOT

Crews from Guy F. Atkinson Construction began  moving the location for southbound I-5 exit 133 north to the vicinity of the Port of Tacoma Road overpass.
Crews from Guy F. Atkinson Construction began moving the location for southbound I-5 exit 133 north to the vicinity of the Port of Tacoma Road overpass.
Crews from Guy F. Atkinson Construction began  moving the location for southbound I-5 exit 133 north to the vicinity of the Port of Tacoma Road overpass. Moving the exit location has the potential to speed up progress on the project. By creating a work zone next to the new southbound I-5 Puyallup River Bridge, crews may be able complete work sooner and move travelers onto the bridge by late summer instead of later this fall. Part of the project calls for the removal of the 1962 I-5 bridges over the Puyallup River.

Construction crews building the I-5 Portland Avenue to Port of Tacoma Road southbound HOV project have found a way to speed up their construction schedule. It means another change is coming for travelers exiting to Tacoma's city center.

Crews from Guy F. Atkinson Construction began moving the location for southbound I-5 exit 133 north to the vicinity of the Port of Tacoma Road overpass. Travelers headed to I-705 and SR 7 will use the same exit and temporary collector/distributor lane as travelers exiting to Portland Avenue and Bay Street.

Construction Details

Once finished, the I-5 Portland Avenue to Port of Tacoma Road southbound HOV project will connect high-occupancy-vehicle lanes to Interstate 5 and SR 16 in Tacoma.

The project also:

  • Builds a new southbound I-5 Puyallup River Bridge;
  • Rebuilds the L Street overpass across I-5;
  • Replaces the original I-5 roadway surface from McKinley Avenue to Portland Avenue;
  • Upgrades signing, lighting and traffic data sensors;
  • Improves storm water collection and treatment facilities;
  • Removes the old 1962 I-5 bridges over the Puyallup River.

Construction/Highway Details:

  • The new decision point for travelers headed to Tacoma's city center exit is 2 mi. before the actual exit.
  • Drivers headed to Tacoma's city center exit 133 will need to be in the right lane of southbound I-5 in Fife before the Port of Tacoma Road exit 136. Signs will be placed to alert travelers as they approach the new decision point.
  • The temporary exit will be in place through spring 2021.

Moving the exit location has the potential to speed up progress on the project. By creating a work zone next to the new southbound I-5 Puyallup River Bridge, crews may be able complete work sooner and move travelers onto the bridge by late summer instead of later this fall.


Today's top stories

New SR 141 Alignment Promises Smoother Travel Through Middle Tennessee

Webber–United JV Advances $620M I-16/I-75 Interchange

Thompson Tractor Hosts Companywide Used Equipment Sale

Georgia Power Begins Construction of Battery Storage System

Werk-Brau Names Gold Coast JCB as South Florida Dealer

BOMAG Names Mid South Machinery Full Line Dealer for State of Mississippi

Louisiana Breaks Ground On $2.3B I-10 Calcasieu River Bridge

James River Equipment Named Newest Trimble Technology Outlet, Serving Customers in Mid-Atlantic


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019