Create a CEG Account  /  CEG Login



First Phase of $55.5M Oregon I-5 Widening Project Continues

Phase one of the $55.5M Oregon I-5 widening project south of Salem is underway, expanding southbound lanes from 2 to 3, replacing bridges, constructing a roundabout, and easing congestion. Scheduled for completion in 2027, the project aims to enhance traffic flow and safety on this vital transportation route.

March 2, 2026 - West Edition #5
Lori Tobias – CEG Correspondent

Multiple cranes move in coordinated formation to lift 160-ft. bridge support beams and place them over Interstate 5.
Oregon Department of Transportation photo
Multiple cranes move in coordinated formation to lift 160-ft. bridge support beams and place them over Interstate 5.
Multiple cranes move in coordinated formation to lift 160-ft. bridge support beams and place them over Interstate 5.   (Oregon Department of Transportation photo) Multiple cranes move in coordinated formation to lift 160-ft. bridge support beams and place them over Interstate 5.   (Oregon Department of Transportation photo) As part of the I-5 widening project from Kuebler to Delaney, crews are pile driving to begin rebuilding the South Commercial Street Bridge.   (Oregon Department of Transportation photo) A drone’s eye view of bridge work on Kuebler to Delaney roads.   (Oregon Department of Transportation photo) Multiple cranes prepare to move beams into position.   (Oregon Department of Transportation photo) A view of the work on I-5 in south Salem, Ore.   (Oregon Department of Transportation photo) Phase one of the project south of the state capital includes widening the southbound stretch of I-5 between milepost 249.5 and 248.9 -- Kuebler and Delaney roads — from two lanes to three lanes.   (Oregon Department of Transportation photo)

Drivers on Oregon's Interstate 5 south of Salem will soon get a break from a historic bottleneck when a new $55.5 million widening project is completed in the coming year.

Oregon Department of Transportation photo

Phase one of the project south of the state capital includes widening the southbound stretch of I-5 between milepost 249.5 and 248.9 — Kuebler and Delaney roads — from two lanes to three lanes, replacing and reconstructing two bridges and an on-ramp and adding a roundabout and new sound walls.

The Salem-based K&E Excavating is the project contractor.

"It will help eliminate a congestion point," said Derek Moore, resident engineer. "I-5 is three lanes all the way from Portland through Salem. As you leave Salem, it narrows down to two lanes, then it widens to three lanes a bit, and then back to two. This project takes out that section of two lanes, so it stays three lanes longer. The key point is that there are some pretty steep hills through there, and you get trucks trying to pass each other, and it slows down things for everybody."

Work on the project began in August 2024, with traffic management on the interstate the major concern. "We were fortunate that there was a kind of a bypass, a detour that we were able to use, so we're able to shift traffic away from where the majority of the work is happening," Moore said.

Oregon Department of Transportation photo

The detour is on an old I-5 alignment that previously served as an exit/entrance ramp. Crews were able to upgrade the ramp so it could be used as part of the detour, Moore said. "So now, we're able to put northbound traffic onto that and put southbound traffic onto the old northbound, so there's a crossover for southbound traffic, and that left us with the southbound alignment free from traffic, so you can do all the work there more efficiently."

The location sees approximately 64,000 vehicles in both directions daily, said Mindy McCartt, an Oregon Department of Transportation (ODOT) public information officer. Traffic was often brought to a standstill by the bottleneck, combined with the trucks attempting to climb the hill.

"One of the ways I describe this particular area is you have to keep commerce moving, especially on I-5," McCartt said. "Commerce is money for the state, and we've got to keep goods and services and people moving through the state, and I-5 is an artery for the state.

"The other thing I like to say is, if you ask an engineer how long it's going to take a bridge, they're going to give you a specific timeline. Then, you tell them they can't shut down traffic, and they triple that number. It's not always just about how long it takes to build the thing; it's how long it takes to build the thing without disrupting the traffic and the movement within Oregon."

Oregon Department of Transportation photo

Since the start, construction crews with K&E Excavating have completed most of the widening, demolished and replaced the bridge over Commercial Street and are building the replacement Battle Creek Bridge.

"It's a single-span girder bridge," Moore said. "We just got done setting all the girders from one end to the other, so they span over I-5. We did three nighttime closures of I-5 while we were setting the beams, sending traffic on a detour route through Salem. That's the majority of the work right now. The bridge is a good winter work because it's not highly dependent on weather."

Equipment on the project includes a Link-Belt RTC-80100, as well as a Grove GMK6350 all-terrain crane.

Coming up, crews will finish work on the Battle Creek Bridge, bring in materials to raise the elevation for a new roundabout at the Battle Creek Road SE and Wiltsey Street SE intersection and finish paving.

"Once that's done, we'll switch southbound traffic back to where it'll be permanently northbound, I-5 will open without traffic and we'll be able to pave and do some repairs through permanent northbound alignment while there's no traffic on it," Moore said.

The major portions of the project are scheduled for completion in the summer of 2026, with the official completion set for the spring of 2027. A second phase for the northbound lanes is planned but unfunded. CEG



Lori Tobias

Lori Tobias is a career journalist, formerly on staff as the Oregon Coast reporter at The Oregonian and as a columnist and features writer at the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.



Today's top stories

IDOT Transforms I-57 With $325M Expansion

USACE Handles Hangar Construction at Fort Riley, Kan.

Making Work Zones Safer

Hayden-Murphy Welcomes Guests to Elk River Open House

APWA Snow Conference Brings Industry Together in Cleveland

Royals, Hallmark Plan $3B Crown Center Stadium Project

New SR 141 Alignment Promises Smoother Travel Through Middle Tennessee

Webber–United JV Advances $620M I-16/I-75 Interchange


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019