Create a CEG Account  /  CEG Login



I-5 North County Enhancement Project Nears End

The I-5 North County Enhancement Project, a partnership between LA Metro and Caltrans, is on track for completion in 2026. The $679 million project aims to improve safety and operations by adding HOV lanes, extending truck lanes, installing sound walls and upgrading infrastructure through Measure R, Measure M, SB 1 and federal funds. Various construction activities and equipment are utilized by OHLA-USA and subcontractors for the project's implementation.

August 4, 2025 - West Edition #16
Irwin Rapoport – CEG Correspondent

The Weldon Canyon Road Bridge was demolished in November 2023 as part of the ongoing I-5 North County Enhancement project.
Caltrans photo
The Weldon Canyon Road Bridge was demolished in November 2023 as part of the ongoing I-5 North County Enhancement project.
The Weldon Canyon Road Bridge was demolished in November 2023 as part of the ongoing I-5 North County Enhancement project.   (Caltrans photo) A bridge is framed as part of the I-5 project.   (Caltrans photo) A retaining wall is constructed between northbound Weldon Canyon Road Bridge and the Calgrove Boulevard off-ramp in April.   (Caltrans photo) Santa Clara River overhead crossing formwork was done in January.   (Caltrans photo) Two views of retaining wall construction are shown here.   (Caltrans photo) Magic Mountain Parkway Bridge column demolition occurred in February 2025.    (Caltrans photo) Metal decking activity on the Rye Canyon Road Bridge happened in January.   (Caltrans photo) The southbound Rye Canyon Road deck pour occurred in March.   (Caltrans photo) An on-ramp is shown under construction and then open to traffic.   (Caltrans photo) Crew tend to the Gavin Canyon Bridge falsework construction in March 2025.   (Caltrans photo)

OHLA-USA crews began working on the Los Angeles County Metropolitan Transportation Authority (LA Metro) and the California Department of Transportation's (Caltrans) $679 million I-5 North County Enhancement project on Dec. 1, 2021, and are on track for 2026 completion.

The project's goal is to improve the operations and safety of Interstate 5 for Santa Clarita Valley motorists, in part by removing trucks from the general-purpose lanes and by adding space for merging.

Caltrans photo

LA Metro planned, designed and is managing the construction in partnership with Caltrans of a project that covers a 14-mi. corridor between State Route 14 in Santa Clarita and Parker Road in Castaic.

The initiative is adding one high occupancy vehicle (HOV)/carpool lane in each direction along I-5; extending the northbound truck lane from SR-14 to Calgrove Boulevard; adding a southbound truck lane from Calgrove Boulevard to SR-14; installing sound walls at four locations; replacing the Weldon Canyon Bridge; installing Intelligent Transportation System improvements between the Interstate 405 and Interstate 210 interchanges; and constructing additional outside lanes.

"The new pavement is JPCP (jointed planed concrete pavement) with significant hot-mix asphalt placed on shoulders and ramps," said Patrick Chandler, LA Metro's media relations manager. "The sound walls are placed with masonry blocks over concrete barriers."

The sound walls on I-5 southbound are north of Hasley Canyon Road between Magic Mountain Parkway and Valencia Boulevard and on I-5 northbound south of McBean Parkway and north of Calgrove Boulevard. Construction began in 2022.

The demolition of the Weldon Canyon Road bridge was completed in 2023.

Caltrans photo

The project is funded through a combination of Measure R and Measure M funding set aside for road and highway projects, along with SB 1 and federal dollars. SB 1 uses state gas taxes and vehicle fees to fund roadways, improve transit and build walking and biking projects.

"This is another example of how SB 1 continues to deliver for the people of California, contributing $247 million — 36 percent of the total project funding — to enhance freight movement between Southern California and the Central Valley Caltrans Director Toks Omishakin said in a news release.

This is a two-stage project.

Stage 1, which began in 2021, should be completed in December, according to an OHLA-USA spokesperson. The includes site staging, median construction, HOV lanes, walls and bridges.

Stage 2 started in April 2024 and will finish in September 2026. It focuses on auxiliary lanes and ramps.

This year is a busy one for OHLA-USA and its subcontractors.

Bridge work is occurring at the Weldon Canyon Road overhead crossing, Castaic Creek, Gavin Canyon undercrossing, Rye Canyon Road, Santa Clara overhead crossing and the Magic Mountain Parkway bridges, according to OHLA-USA.

Walls-wise, crews are tackling the outside shoulder retaining walls — northbound and southbound I-5 between SR-14 and Parker Road, sound walls along southbound I-5 at Hasley Canyon Road and between Magic Mountain Parkway and Calgrove Boulevard both northbound and southbound.

For shoulders and ramps, efforts are ongoing for drainage, barrier, signage and pavement work project-wide; outside lane reconstruction; and temporary pavement and new construction of the northbound truck route on-ramp. Center median activities are focusing on barriers, signage and lighting throughout the project, an OHLA-USA spokesman said.

The construction of the Gavin Canyon undercrossing bridge had crews installing falsework throughout the spring. In March, a large crawler crane lifted heavy elements of the system at night. The crane operator and personnel assisting in the placement of the pieces coordinated their actions. The bridge should be delivered in December.

Caltrans photo

In February, crews demolished the columns of the Magic Mountain Parkway Bridge between The Old Road and Tourney Road. Bridge construction continues, including reductions of eastbound and westbound shoulder widths.

As for the two-span concrete Castaic Creek Bridge, falsework was installed and concrete pours for the deck were made throughout the spring. The superstructure is anticipated to be complete this summer, according to OHLA-USA.

The construction of the Rye Canyon Road Bridge is proceeding, too, with the metal decking placed in January. The left-side bridge extension was completed in the spring and the right-side bridge demolition will soon occur. The work to install the bridge deck will take the rest of the year.

The construction of the Calgrove Boulevard undercrossing and southbound on-ramp was completed in June, with the approach slabs at the undercrossing installed in April.

Work also included the southbound on-ramp roadway excavation and construction, concrete and asphalt paving, electrical work and metal beam guardrail installation.

Major form work for the Santa Clara overhead crossing began in January.

Abutment, forming, superstructure work, rebar installation and concrete work is ongoing throughout the summer.

The building of the Castaic sound wall on southbound I-5 between Villa Canyon Road and Hasley Canyon Road began in the spring and will continue throughout the year. Crews are installing masonry blocks in an excavated lane that separates them from traffic. The construction is proceeding in a north-south trajectory.

Construction of the sound wall between Magic Mountain Parkway and Valencia Boulevard started in April, with delivery at the end of the year. Crews are installing transparent panels.

Construction of the Calgrove Boulevard. sound wall will begin this summer. Starting activities include scaffolding and block installations. It should be finished by winter.

Caltrans photo

Other activities include ramp and outside shoulder improvements, including the northbound truck route, concrete paving, striping and drainage and electrical work. Overhead signs are being installed between Calgrove Boulevard and SR-14 throughout the summer.

Dust mitigation and stormwater management are based on fugitive dust and stormwater management administered by environmental engineers. Mitigations include water trucks for dust, slope erosion control, track-out control, reduced vehicle speeds, covering inactive stockpiles and storm drain protections.

OHLA-USA has a plethora of subcontractors and material suppliers on the project. Those include Sequoia Consultants, Global Transloading LLC, Hunsaker & Associates, Cooper Engineering Inc., IMRAE Corp., Rock Structures Construction Co., Cal-Stripe Inc., Tipco Engineering Inc., Endemic Environmental Services Inc., Condon-Johnson Associates Inc., CGO Construction and Ferreira Construction Co.

Other included Don H. Mahaffy Drilling Co., High Light Electric Inc., Global Road Sealing Inc., Integrity Rebar Placers, LA Steel Services, Reycon Construction Inc., Cell-Crete Corp., Diverscape Inc., Calmex Engineering Inc., Apex Universal Inc., Lowers Welding and Fabrication Inc., Lowers Industrial Supply, Angelus Block Co. Inc. and National Ready Mix Inc.

OHLA-USA used a massive amount of equipment on the project, including a Terex Bid-Well paver and Terex T 340 hydraulic truck cranes; GOMACO GP2600-pavers, Commander III pavers; TC600 cure machines and a RTP5-00 placer; various Cat pieces: a 950 wheel loader, a D6T dozer, a 140M3 motor grader, a 314F wheeled excavator and 335F LC excavators; and Genie GS-4069 and GS-3369 RT scissor lifts and S-85XC and S-40 boom lifts.

Also used were John Deere 210EP and 135G excavators; Komatsu PC360 and PC35MR excavators and D39PX dozers; Grove GRT880 cranes; Volvo ECR88D and ECR145L excavators, SD115B rollers and SD45B smooth drum compactors; and Bobcat T740 compact track loaders and MT100 mini track loaders.

Skytrack, JLG, Kubota, Hyundai, Xtreme, Chem-grout, Magni, Dynapac, Hamm and Bomag were well represented on the many construction sites. CEG



Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.



Today's top stories

IDOT Transforms I-57 With $325M Expansion

USACE Handles Hangar Construction at Fort Riley, Kan.

Making Work Zones Safer

Hayden-Murphy Welcomes Guests to Elk River Open House

APWA Snow Conference Brings Industry Together in Cleveland

Royals, Hallmark Plan $3B Crown Center Stadium Project

New SR 141 Alignment Promises Smoother Travel Through Middle Tennessee

Webber–United JV Advances $620M I-16/I-75 Interchange


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019