Create a CEG Account  /  CEG Login



MDOT Makes Progress On North Mississippi Projects

MDOT updates progress on various projects in North Mississippi. Highlights include bridge replacements and road enhancements on State Route 9, U.S. 51, and I-55. Projects are set for completion between 2026 and 2029.

February 26, 2026 - Midwest Edition #5
Mississippi Department of Transportation

Work continues on the replacement of the U.S. 51 bridge over the Yocona River in Yalobusha County, Mississippi.
MDOT photo
Work continues on the replacement of the U.S. 51 bridge over the Yocona River in Yalobusha County, Mississippi.
Work continues on the replacement of the U.S. 51 bridge over the Yocona River in Yalobusha County, Mississippi.   (MDOT photo) Officials break ground for the State Route 7 widening project in Oxford, Miss.   (MDOT photo)

The Mississippi Department of Transportation (MDOT) has released updated progress reports on several construction and maintenance projects across north Mississippi.

State Route 9 — Calhoun County

MDOT continues work on replacing four bridges on State Route 9 south of Calhoun City. At Site 1, crews are addressing bridge deck issues with plans to reopen the roadway before year end. At Site 2, two of three asphalt lifts have been completed.

The $24 million contract, awarded to Manhattan Road & Bridge Company of Little Rock, Ark., is scheduled for completion in spring 2026.

U.S. 51 in Yalobusha County

Construction is advancing on the replacement of four bridges along U.S. 51. Site 1 is complete, and traffic has returned to the original alignment. At Site 2, detoured traffic remains in place while deck pours and rail installations are finished. Site 3 substructure work is under way, including removal of the old bridge and installation of piling and concrete. Site 4 traffic will shift once detour bridges are complete.

This $20.1 million project, awarded to Talbot Brothers Contracting Co. Inc. of Nesbit, is expected to conclude in summer 2026.

U.S. 51 Over Yocona River in Yalobusha County

All bridge and rail pours are complete on the U.S. 51 bridge over the Yocona River. Crews are awaiting warmer temperatures to place approach asphalt. Construction of the box culvert north of the river is finished, and riprap reinforcement has been installed. Final stone dike placement depends on river levels.

Century Construction of Tupelo holds the $12.2 million contract, with completion anticipated in spring 2026.

State Route 7, University Avenue in Oxford

Construction of new roundabouts at the State Route 7 ramps and University Avenue continues, with all ramps remaining open. Traffic currently uses the interior lanes while work proceeds along the outside roadway. Drainage, curb and gutter and concrete work are complete.

Cook & Son LLC of Smithville is executing the $4.9 million contract, scheduled for completion in spring 2026.

U.S. 51 in Carroll County

Replacement of six bridges along U.S. 51 is progressing. Five concrete decks are complete, with crews now working on the remaining structures. All piling and caps are finished, beams are installed and deck installation is under way on the final bridge. Roadway embankment work is nearly complete, and limestone base installation at Site 1 is finished pending asphalt.

Ste Bil Grading Inc. is leading the $15.9 million project, expected to finish in fall 2026.

U.S. 278 / State Route 6 in Panola County

A 14-mi. mill and overlay project is under way, with mainline paving complete. Remaining work — including permanent striping, grinding and clay gravel placement — will resume with warmer weather.

Lehman Roberts Company of Memphis, Tenn., is managing the $13.6 million contract, scheduled for completion this fall.

I-55 / I-69 in DeSoto County

MDOT continues asphalt milling and overlay of approximately 4 mi. of I-55 and I-69 between I-269 and Church Road. New asphalt has been placed on travel lanes and shoulders, and ramp paving and final striping will follow. Work has paused for winter and will resume in spring 2026.

The $5.3 million project is being performed by Lehman Roberts Company.

State Route 302 in DeSoto County

An 8 mi. nighttime mill and overlay project from Airways Boulevard to U.S. 78 is scheduled to begin in spring 2026.

APAC–Tennessee Inc. of Richland, Tenn., was awarded the $10 million contract, with completion expected in fall 2026.

State Route 7 Widening in Oxford

This project will expand SR 7 to four lanes between Belk Boulevard and County Road 370 and includes grading, drainage, bridge construction and paving.

Talbot Bros. Construction holds the $138.7 million contract. Completion is estimated for fall 2029.


Today's top stories

IDOT Transforms I-57 With $325M Expansion

USACE Handles Hangar Construction at Fort Riley, Kan.

Making Work Zones Safer

Hayden-Murphy Welcomes Guests to Elk River Open House

APWA Snow Conference Brings Industry Together in Cleveland

Royals, Hallmark Plan $3B Crown Center Stadium Project

New SR 141 Alignment Promises Smoother Travel Through Middle Tennessee

Webber–United JV Advances $620M I-16/I-75 Interchange


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019