The Nevada Department of Transportation (NDOT) began a $41 million federally funded pavement preservation project on U.S. 95 in Clark County in late February, improving roadway conditions on a key corridor south of Boulder City.
Las Vegas Paving Corp. is the contractor.
The project spans approximately 17 mi. of U.S. 95, from approximately 7 mi. north of Nelson Road to nearly 3 mi. south of the Interstate 11 junction (mileposts 37.85 to 55.15).
Work includes milling and resurfacing the roadway, as well as repairing damaged pavement. Additional improvements include updated striping and signage, drainage and lighting upgrades and installation of tortoise fencing.
Construction is anticipated to be completed by winter 2026, weather permitting. During active construction, the speed limit will be reduced to 55 mph through work zones for the safety of both drivers and construction crews.
The schedule is subject to change due to weather or other factors.