North Carolina Orders Penalties for Delays on Interstate-77

May 18, 2017 - Southeast Edition
Construction Equipment Guide

North Carolina officials are imposing penalties on the company building toll lanes on Interstate 77 north of Charlotte because of delays in clearing the road after overnight construction.

Local media outlets report the North Carolina Department of Transportation has told the builders that the state will withhold about $1.3 million from the next payment.

Transportation officials say I-77 Mobility Partners failed to end lane closures on I-77 North until 7:45 a.m. Tuesday. Ramps on I-277 east and west were not opened until 8:05 a.m.

In both cases, the lanes were supposed to reopen at 5 a.m.

The lane closures caused massive traffic problems in the state's largest city.

An I-77 Mobility Partners official did not immediately respond to a request for comment.—AP


Today's top stories

New SR 141 Alignment Promises Smoother Travel Through Middle Tennessee

Webber–United JV Advances $620M I-16/I-75 Interchange

Thompson Tractor Hosts Companywide Used Equipment Sale

Georgia Power Begins Construction of Battery Storage System

Werk-Brau Names Gold Coast JCB as South Florida Dealer

BOMAG Names Mid South Machinery Full Line Dealer for State of Mississippi

Louisiana Breaks Ground On $2.3B I-10 Calcasieu River Bridge

James River Equipment Named Newest Trimble Technology Outlet, Serving Customers in Mid-Atlantic


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019