PennDOT to Begin Girard Point Bridge Rehabilitation, Improvement Project in Southwest Philadelphia

PennDOT will begin a $261.5M, two-phase Girard Point Bridge rehab project in Southwest Philadelphia. Construction starts Jan. 12, 2026, with minimal traffic impact until events like the FIFA World Cup. Expected completion is early 2031 with complex repairs and improvements planned.

January 5, 2026 - Northeast Edition
PennDOT

Map of the Girard Point bridge project limits.
PennDOT map
Map of the Girard Point bridge project limits.

The Pennsylvania Department of Transportation (PennDOT) announced that construction will begin on Jan. 12, 2026, on the $261.5 million, two-phase project to rehabilitate the Interstate 95 Girard Point Bridge and nine approach structures in Southwest Philadelphia.

Initial construction activities under phases one and two through mid-February 2026 will be limited to mobilization and construction of contractor access roads at various locations under I-95 between Enterprise Avenue and FDR Park Drive. No travel restrictions are planned on I-95 at this time.

Once construction starts later in winter 2026, PennDOT will maintain three lanes of traffic in each direction on I-95. To accommodate travelers to the FIFA World Cup and the MLB All-Star game, PennDOT will work to minimize traffic impacts until these events are completed.

In late July 2026, long-term construction patterns maintaining three travel lanes during peak hours will be installed, while frequent off-peak and weekend lane restrictions will be coordinated with other regional events, including those at the sports complex in South Philadelphia.

Under phases one and two, the main 5,183-ft., double-decked I-95 Girard Point Bridge and nine approach structures between Enterprise Avenue and Broad Street (Route 611) will be repaired.

Improvements include:

• rehabilitating the bridge deck, including the application of a Latex Modified Concrete (LMC) overlay and improving the decks' expansion joints;

• replacing the bridge parapets (barriers);

• rehabilitating and painting select areas of steel superstructure;

• rehabilitating substructure concrete;

• replacing and improving the bridge's lighting and drainage systems;

• installing protection and scour remediation for the main Girard Point Bridge pier in the Schuylkill River; and

• upgrading Intelligent Transportation Systems (ITS) on I-95.

Ten additional approach structures will be repaired under phase three of the project, which is expected to start at the completion of phase two. phase four, not yet scheduled, will repaint the main bridge. The entire project is expected to finish in early 2031.

South State Inc. of Bridgeton, N.J., is the general contractor on phases one and two.

The project is financed with 90 percent federal and 10 percent state funds and is part of PennDOT's Bridge Preservation Program to ensure the structural integrity and rideability of Pennsylvania's bridges.

For more information, visit pa.gov/agencies/penndot/projects-near-you/district-6-projects/girard-point-bridge-improvement-project.


Today's top stories

New SR 141 Alignment Promises Smoother Travel Through Middle Tennessee

Webber–United JV Advances $620M I-16/I-75 Interchange

Thompson Tractor Hosts Companywide Used Equipment Sale

Georgia Power Begins Construction of Battery Storage System

Werk-Brau Names Gold Coast JCB as South Florida Dealer

BOMAG Names Mid South Machinery Full Line Dealer for State of Mississippi

Fayetteville's I-295 Project Wins Award for Unique Solution

Caterpillar Opens Registration for Global Innovation Challenge


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019