Zodiac-Poettker HBZ JV II Nears Completion of Hunter Army Airfield Aircraft Maintenance Hangar

Zodiac-Poettker HBZ JV II is nearing completion of a $56.4 million Aircraft Maintenance Hangar at Hunter Army Airfield in Georgia, designed for Apache AH64 and Blackhawk UH60 helicopters. The 119,500-sq.-ft. hangar features specialized facilities, green spaces and aims for LEED Silver certification. Challenges like concrete placement and utility considerations were managed as construction nears final stages.

August 27, 2025 - Southeast Edition #18
Irwin Rapoport – CEG Correspondent

The Attack/Assault Battalion (AAB) Aircraft Maintenance Hangar begins taking shape.
U.S. Army Corps of Engineers photo
The Attack/Assault Battalion (AAB) Aircraft Maintenance Hangar begins taking shape.
The Attack/Assault Battalion (AAB) Aircraft Maintenance Hangar begins taking shape.   (U.S. Army Corps of Engineers photo) The hangar, designed to service Apache AH64 and Blackhawk UH60 helicopters, is established on a former motor pool area, which had a concrete apron ranging from 8- to 12-in. thick.   (U.S. Army Corps of Engineers photo) Cranes were crucial for the building construction, particularly for the steel-setting elements.   (U.S. Army Corps of Engineers photo) Concrete pouring took place at night and during the early morning due to the heat.   (U.S. Army Corps of Engineers photo) The future hangar site after initial earthwork was completed.   (U.S. Army Corps of Engineers photo) The hangar project dates to 2021.   (U.S. Army Corps of Engineers photo) Construction crews are now tackling punch list items as the project nears completion.   (U.S. Army Corps of Engineers photo)

Zodiac-Poettker HBZ JV II LLC is four to five months away from turning over the $56.4 million Attack/Assault Battalion (AAB) Aircraft Maintenance Hangar at the Hunter Army Airfield near Savannah, Ga.

The project began on Aug. 11, 2021, and is 95 percent complete.

The joint venture partners are Poettker Construction Co. and Zodiac Inc.

U.S. Army Corps of Engineers photo

The United States Army Corps of Engineers (USACE) awarded the contract for the 119,500-sq.-ft., six-bay helicopter maintenance hangar in June 2021. The hangar has approximately 44,000 sq. ft., and the two-story administrative section has approximately 75,000 sq. ft. of interior space.

"The hangars at the airfield date back to the 1940s," said Todd McGalliard, a resident engineer for the airfield and the contract's administrative contracting officer. "So, the Army decided to build a new facility, since retrofitting an existing facility was not cost-effective."

The hangar, designed to service Apache AH64 and Blackhawk UH60 helicopters, is established on a former motor pool area, which had a concrete apron ranging from eight to 12 in. thick.

The rectangular-shaped structure includes a hazardous materials storage facility and a petroleum/oil/lubricant storage section. Supporting the hangar is a ground support equipment storage building, mobile shop storage shed, water tower, storage yard, hangar access apron and aircraft washing apron with a wash access apron.

Most of the building is clad in brick, along with insulated prefabricated sandwich metal panels for the hangar door and metal panels near the top of the hangar side. It has several building systems, including HVAC, fire suppression, electrical, IT, drainage and the collection of oils and greases. The site has 108 surface parking spots.

The repair bay adjacent to the airfield has a metal beam structure complete with a high-powered lighting system. Helicopters can easily enter the bay area for repairs and routine maintenance. The opening for the hangar is large enough for helicopters to roll in with rotors fully out.

The hangar project, which included an increased green space with two bioretention areas, was designed by the USACE and is trying to meet the Leadership in Energy and Environmental Design (LEED) Silver certification criteria.

"We increased the green space by the parking area and added two bioretention areas," McGalliard said. "That was factored into the LEED Silver points. Additionally, the concrete that was removed was recycled and reused in other areas for Department of Public Works or in other forms of construction."

Lasting Structure

The new building was designed with a 50-year minimum lifespan.

"We have seismic activity in this area," said McGalliard, "but there was nothing out of the normal design and construction practices for this area. There were a lot of concrete blocks and a 48-in. concrete drainage structure that had to be rerouted around the building. The design challenges were more upfront, and it was planned for with the JV's construction techniques and sequencing in mind."

The USACE has Centers of Standardization to ensure installations meet common expectations in terms of capabilities, capacities and throughput.

U.S. Army Corps of Engineers photo

"We incorporate lessons learned from past designs and ensure they are site adapted," McGalliard said. "This hangar was designed locally at the Savannah District Engineering Division. We incorporated some enhancements, such as the workstations, which have the ability to power the helicopters; a compressed air system; data cabling that allows for computer connectivity; the mechanical shops that incorporated a lot of ventilation and safety measures; as well as the installation of overhead cranes."

Construction at an active airfield is never easy.

This has primarily been a daytime operation, with only concrete placement taking place at night and during the early morning, due to the usual heat.

Project Challenges

The concrete placement was challenging at times, since utility installation was a consideration.

"Concrete placement could be challenging, depending on where we were placing it," said McGalliard. "Sometimes utilities were encased by concrete, and sometimes they were below the concrete footers. If the utilities are within the building, they could be under the slabs or through the footers and walls. Outside of the building, we try to avoid placing concrete over the utilities, but with concrete paving, utilities will sometimes be underneath, so we place clean outs where needed for access along with other measures.

"[The project] has some special requirements in paving, and the process was very technical and meticulous in its placement," he said. "It is very different compared to a normal concrete footer or slab. … We have very high standards and detailed specifications that contractors must meet for testing, thickness, elevation and strength characteristics above and beyond normal foundation and slab concrete."

Standard construction methods were followed.

U.S. Army Corps of Engineers photo

"We had footers that had to be placed below grade," said McGalliard, "and then we have the stem walls, slab, bearing walls, second-floor concrete deck and the load-bearing walls that are going up with the concrete tie-beams at the top of the masonry walls."

For the concrete placement, Millstone Webber and AB Construction used a telebelt — a truck with a large boom that has a hopper where concrete mix trucks empty their load. From there, a conveyer fed from the hopper is placed in front of the triple-tube screed machine.

Following the motor pool removal, the JV focused on constructing the hangar building.

"All the utilities within the building are new," said McGalliard. "We tied into the water mains and then extended them. For power, there was a major feed line that had to be relocated from underneath the new building footprint. We also included a new transformer and a new natural gas line."

Inside the building are water, sewer, a fire suppression system and a 200,000-gal. fire suppression holding tank, plus a foam fire suppression system.

The hangar bay is composed of a structural steel frame, while the administrative section is concrete masonry framed with a composite steel and concrete deck. The roof is a structural steel system.

The first step was to remove the concrete surface for the motor pool.

"The concrete removal went very well," said McGalliard. "They used a guillotine-type concrete buster attached to the back of a large utility truck. It helped that the concrete had limited reinforcement, making it easier to break up. They set up a sorting/crushing plant to crush the concrete and graded it for different gradations and purposes. Any reinforcing material was separated and recycled."

Excavation operations were minimal, as only footers and holding tanks were placed below grade.

Cranes were crucial for the building construction, particularly for the steel-setting elements.

"The highest point of the steel is 50 feet," said McGalliard. "We had very large structural steel girders that spanned over 130 feet, and we used two cranes to set it."

The cranes worked in tandem, with each lifting an end and setting it on the columns.

"This was done three times," McGalliard said. "After that, another crane was used for setting the rest of the structural steel in the hangar. There wasn't a lot of need for cranes on the administrative side."

Punch List Phase

Aside from some minor construction work, the focus is on a long and detailed commissioning process to ensure the internal systems are working properly.

U.S. Army Corps of Engineers photo

"For the hangar side, we're finishing up the floors, and the doors still need some finish work," McGalliard said. "We are down to the fine-tuning part of the project, making sure everything works the way it's designed to, and the construction meets all the requirements."

Construction materials include approximately 2,600 cu. yds. of structural concrete in the building footprint and 3,000 cu. yds. for airfield paving.

Typical days have 60-70 workers on site with high points of up to 120.

Subcontractors include Milestone Webber for concrete paving, AB Construction for concrete placements and Pyramid for the masonry, along with dozens of other subcontractors.

Equipment operators used several pieces, including a triple-tube roller screed, a telebelt, a rubber track placer, a motorized paving bridge for airfield paving and paving train, telehandlers, dozers and excavators. CEG

(All photos courtesy of the United States Army Corps of Engineers.)



Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.



Today's top stories

New SR 141 Alignment Promises Smoother Travel Through Middle Tennessee

Webber–United JV Advances $620M I-16/I-75 Interchange

Thompson Tractor Hosts Companywide Used Equipment Sale

Georgia Power Begins Construction of Battery Storage System

Werk-Brau Names Gold Coast JCB as South Florida Dealer

BOMAG Names Mid South Machinery Full Line Dealer for State of Mississippi

Fayetteville's I-295 Project Wins Award for Unique Solution

Caterpillar Opens Registration for Global Innovation Challenge


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019