Auditor Blames State for Costly Bridge Boondoggle

"Excessive" delays plague a project that started without a proper inspection.

December 4, 2015 - Northeast Edition
Construction Equipment Guide

BOSTON (AP) - Massachusetts Auditor Suzanne Bump’s office blames the state Department of Transportation for excessive delays that have wasted up to $2.6 million in repairs to a Gloucester bridge.

The transportation department set out to repair the A. Piatt Andrew Bridge, which carries Route 128, in 2006 after the bridge had been given a structural rating of ”serious’ in August 2005.

The auditor’s report says transportation workers would have saved years of work and millions of dollars if they inspected the bridge before beginning construction.

Instead, the report says crews relied on an outdated inspection that didn’t include several significant structural issues found only after work had begun.

Transportation department officials say inspections are now performed before designs are started on repair and preservation contracts.


Today's top stories

Faster Where It Counts: How Excavator Cycle Time Shapes Jobsite Productivity

4Rivers Equipment's 'One Big Goal' Passes Halfway Mark

New OU Basketball Arena Under Way at Entertainment Complex in Norman

Big Crowd Descends On New Auction Facility in Uncasville

Demo & Dig Days Events Draw Northeast Operators

UConn Receives Volvo L20 to Grow Construction Education

Mosquito Road Bridge Work Requires Unique Techniques

Columbus Bypass Project Advances Along 6 Mi. of I-10


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019