Report: Nuclear Weapons Plant Mercury Cleanup Could Cost $3B

A U.S. Department of Energy report says the cleanup of mercury contamination at a Tennessee nuclear weapons plant could cost between $1 billion and $3 billion.

June 15, 2016 - Southeast Edition
Construction Equipment Guide

The Oak Ridge National Laboratory.
The Oak Ridge National Laboratory.

OAK RIDGE, Tenn. (AP) — A U.S. Department of Energy report says the cleanup of mercury contamination at a Tennessee nuclear weapons plant could cost between $1 billion and $3 billion.

The Knoxville News Sentinel (http://bit.ly/1rnWDV3 ) reports that the report outlines technology plans for mercury cleanup at the Y-12 nuclear weapons plant at Oak Ridge, which used mercury during the Cold War to develop hydrogen bombs.

The DOE says that mercury seeped into soil and leaked into local waterways. It also noted that mercury can move during efforts to deactivate and decommission the plant's old buildings. Another concern is the presence of methylmercury, the most toxic form of the metal, in a nearby creek.

Information from: Knoxville News Sentinel, http://www.knoxnews.com


Today's top stories

Route 61 Project Eliminates Deadly Curve

Medico Construction Equipment Celebrates New Facility

Sales Auction Company Holds 17th Annual Spring Sale

Big Crowd Descends On New Auction Facility in Uncasville

Demo & Dig Days Events Draw Northeast Operators

UConn Receives Volvo L20 to Grow Construction Education

Columbus Bypass Project Advances Along 6 Mi. of I-10

Faster Where It Counts: How Excavator Cycle Time Shapes Jobsite Productivity


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019